|
Construction of the New York, New Haven & Hartford
New High Speed Electric Line Running North from New York City.
By Gilbert O. Browne. Published in Railway Age
Gazette, June 7, 1912.
The New York, Westchester & Boston Railway, part of which was
put in operation last week, is a four-track electric line owned by the
New York, New Haven & Hartford. It runs from White Plains, N. Y., to
174th Street, New York City, where it joins the Harlem branch of the
New York, New Haven & Hartford, and when completed will be operated as
a part of that system. Beside connecting with the Harlem branch at
174th Street, interchange of traffic will be made with the West Farms
branch of the Interborough Rapid Transit subway at 180th Street and
Morris Park Avenue. There is also a branch connecting with the New
Haven main line at New Rochelle.
The proposition of building a line along the general location
of the New York, Westchester & Boston is not new. The original
company was formed many years ago, and right-of-way was purchased from
time to time. About ten years ago actual construction work was begun
on the southern end of the road, but the company was unable to finance
the project and was forced to give it up. Later, control of the road
was bought by the New York, New Haven & Hartford, which
relocated the line, and commenced construction work in 1908.
Throughout its entire length, the line has been built to
conform with the main line standard of the New Haven. The rail is
100-lb. section and creosoted ties with 22 in. of ballast are
used. All bridges are of concrete and steel, and have been designed to
stand heavy traffic at high speed. They are all waterproofed. The
road will be operated by single phase current as a part of the New
Haven electrical system, and multiple-unit trains will furnish the
passenger service. There will be no freight service for the present.
It is four-tracked from 174th Street to Mount Vernon, where two tracks
diverge to White Plains, and two to New Rochelle. The entire line
will be fenced in private right-of-way, protected with block signals
and free from grade crossings.
The maximum grade is 1.0 percent, except for one stretch of
2.5 percent from 174th Street, the junction with the Harlem branch
tracks, to the south end of the West Farms Viaduct at 177th Street.
The adjustment of alignment and grade at this point was one of the
most difficult problems which the engineers encountered and the
present location was adopted only after trying and discarding many
others. Certain fixed street grades over which the tracks must have
sufficient clearance, certain other points, like the junction point,
at which the elevation was fixed, added to difficulties in obtaining
right-of-way. All served to confine the possible solutions within
narrow limits, and made the task one not so much of choosing the best,
but of avoiding the worst. It was finally decided to carry the tracks
over 177th Street, and this extraordinary grade was necessary to give
the tracks sufficient clearance. The curvature is limited to 4 degs.,
except for one 6-deg. curve through Mount Vernon.
From the Harlem river to about 174th Street the road will be
operated over the tracks of the Harlem River branch, which will be
completed so as to be available for such operation under a contract
granting perpetual rights to the New York, Westchester & Boston. Just
north of the present West Farms station on the joint tracks, the road
diverges from the Harlem, and after crossing upper West Farms on a
four-track steel viaduct 2,000 ft. in length, makes its first
independent stop in the transfer station at 180th Street, near the
eastern border of Bronx Park. The plans for this station call for a
steel and concrete structure, 200 ft. wide by 540 ft. in length. Half
a mile north the road crosses over the Morris Park viaduct. This
viaduct is of reinforced concrete 400 ft long, and varying in height
from 20 to 30 ft. It is very carefully designed architecturally, to
secure a pleasing effect, so that the value of the surrounding
property for residential purposes might not he impaired. The walls
rise several feet above the track and have been finished with great
care to add as much as possible to the appearance of the structure.
All exposed surfaces are dense and smooth, and all exposed edges
chamfered.
 | | Typical Cross-Section of Pelham Park
Subway |
Immediately north is the Pelham Park subway, three quarters of
a mile long. The company was forced to build this subway, instead of
leaving an open cut, in order to obtain the right-of-way. After the
cut was made, concrete piers were sunk and on these piers the steel
framework was built. The general type of steel work is shown in the
accompanying photograph and cross section. After the erection of the
steel, the side walls and the top were filled in and the whole then
waterproofed. It was then back-filled to the original grade.
The interesting problem connected with the building of this
subway was that of adjusting the grade and section of roof members to
the conditions imposed by the varying levels of the streets which
cross the subway. The clearance from base of rail to underside of
roof is 18 ft. 6 in. Where the level of the street was higher than the
average, the difference was taken care of partly by varying the
gradient and partly by making a deeper and therefore more economic
section of the I-beams in the roof structure. As few variations in
section were made as consistent with economy so as to facilitate
fabrication and erection. Another problem about which there was
considerable discussion was as to the footings of the columns of the
sidewalks. The base of the column rests on the same level as the floor
of the subway. Some 3 in. from the near side of the column base a
concrete wall 9 in. thick and 12 in. high was made, the intention
being after the walls were in place to fill in the space between the
column bases and this wall with concrete. There was some question as
to whether this, combined with friction, would be sufficient to
withstand the earth thrust. After the roof members and side curtain
walls were in place, there was a heavy slide of material from the
sides of the cut at one point, which forced the whole steel structure
out of place, driving the bases of the columns up against the 9
in. wall, which held. This practical test settled any doubts. In
general, to resist side pressure the whole subway structure acts as a
unit, the floor system and the roof system dividing the horizontal
thrust. At the station in the southerly end of the subway, and at the
one in the middle, the stairway wells make it impossible to continue
the integrity of the roof system, so at these points concrete
retaining walls on each side of the subway are put in to take care of
the earth pressure. The waterproofing is four-ply Barrett
specification.
|
|  |
 |
|
Steelwork for Pelham
Park Subway |
Subway with Brick and
Concrete Completed and Backfill Under Way |
From this point to the East Sixth Street station at Mount
Vernon there is comparatively light work, most of it embankment. East
Sixth Street marks the southern end of the cut through Mount
Vernon. This cut is from 20 to 40 feet deep, and is almost solid rock
throughout. From the northern end of this cut the tracks run out upon
the Columbus Avenue Viaduct. This viaduct is about 400 ft. in length,
including the through girder bridge of 104 ft. span over the main line
of the New York, New Haven, & Hartford R. R. The main girders are
supported by towers resting on concrete pedestals; these towers are
made up of 10-ft. girders supporting the main girders and resting upon
H columns. In this structure each end of every longitudinal girder
rests on a column and never on a transverse girder. This results in
what at first sight appears a peculiar arrangement of columns in some
places, particularly near the crossing of the New Haven tracks and the
streets just north of the tracks. The columns are built up of
3/4in. plates and 3 in. single-bars, and their bases rest on
3/4in. bed-plates 48 in. x 56 in.
 | Bridge near Southern Portal of Pelham
Park Subway |
The girders used in the span over the New Haven tracks are
exceptionally heavy, those in the center supporting two tracks
weighing 90 tons apiece, and the outside ones, 54 tons. The distance
between bearings is 104 ft. and the depth of the girders 10 ft. 6 in.
The erection of this span was most interesting. The viaduct was built
from the north end, as there was no point to the southward at which
the steel could be brought in economically. The traveler used in the
erection of the viaduct could handle the outside, 54-ton, girders
alone, but not the three heavy girders. After the abutments and piers
were built, the steelwork was erected up to the abutment north of the
New Haven tracks. The two light girders were then erected by the
traveler, one at a time, close together in a temporary position on
about the center line of the bridge, the girders being lifted from
freight cars on the New Haven tracks below, as shown in the
accompanying photograph. A temporary floor system was put on these
girders and a track laid. A derrick car was then run under the
traveler and over this temporary track to the south abutment, from
which position it erected the first span of the viaduct south of the
abutment. Tracks were laid on this span and the derrick car run out
on it (having first, of course, to be run back over the traveler and
to the nearest point where it could be turned around so as to face the
work on the long span over the New Haven tracks). Skids, consisting
of rails on grillage, were then put on the two abutments. Two of the
heavy girders were then lifted up from the New Haven tracks, each
being handled by the derrick car and the traveller working
together. These girders were put in temporary positions on the skids
at each side of the light girders. The temporary track and floor
system under the light girders were then removed and these girders
were lifted out to their final positions. The two heavy girders were
then moved on the skids to their final positions, which could not have
been done before because of the position of the temporary track; and
the third girder was lifted direct to its final position.
|
|  |
|  |
|
| Cut Through Mount
Vernon |
Typical Concrete
Bridge |
A few hundred yards north of this viaduct is the junction
point where the tracks diverge, two running east through New Rochelle
to the New Haven main line, and two extending north through
Eastchester, New Rochelle and Scarsdale to White Plains. Immediately
upon leaving the junction the former cross the Hutchinson River on a
steel concrete floored viaduct 700 ft. long. The general type of
construction of this viaduct is very similar to that of the Columbus
Avenue viaduct. At Fifth Avenue, North Pelham, is a large concrete
arch bridge which carries the tracks over the avenue below. The
structure was designed to be a station also, and the combination is
very effective. Between the station and Webster Avenue, half a mile
north, there is considerable heavy cutting, and from Webster Avenue
the road drops down for nearly a mile on a 1 percent grade to the
junction with the New Haven main line.
The White Plains branch extends northward after leaving
the junction point and runs over a 30-ft. fill for several hundred
feet before it also crosses the Hutchinson River. This fill, while not
very large, is mostly earth and has given much trouble from settling
particularly when concrete piers for the catenary bridges, which carry
the electric contact wires, were being set. The bridge over the
Hutchinson River is a single span deck girder, 105 feet long. Except
for the cut at Wykagyl Station and the Essex Road crossing, there is
comparitively little heavy work between this point and the heavy cut
south of Quaker Ridge Station.
|
|  |
|  |
|
Typical Tower
of Columbus Avenue Viaduct
|
Heavy Girders Used in
Span Over New Haven Tracks |
At Heathcote, a mile north, the site of the station was at the
intersection of Heathcote Road and Palmer Avenue, all upon the same
grade. Both roads were therefore raised for several hundred feet back
from the station and are now carried over the tracks on steel girder
bridges.
Norton Avenue, which crosses the line half a mile from
here, marks the southern end of a solid rock cut, less than 500
ft. long, but over which the company has had to build three bridges
for street crossings. At Mamaroneck Avenue a tunnel section is used
under the surface car tracks. The Mamaroneck Avenue cut, over half a
mile in length, is the longest on the White Plains branch, and
furnished much of the material for the great fill just north of it,
which marks the White Plains station, the terminal of the line. Just
before leaving the cut, the two tracks are increased to four, the two
inside tracks are carried on a slightly rising grade to enable them to
be carried on over the city when the Westchester Northern is
completed. The outside tracks descend to the station and yards.
 | | Columbus Avenue Viaduct, Looking
West |
The system of electrification used on the New York,
Westchester & Boston is the same as, in fact, a part of the general
New York, New Haven & Hartford system; namely, a single-phase current
of 11,000 volts on the contact wire, and a system frequency of 25
cycles. In adopting the voltage of 11,000 on the contact wire, the
New Haven road has planned with the idea of permitting the operation
of any adjacent company's equipment upon its own lines, or vice versa.
This voltage is recommended as a minimum potential, it being
recognized that there is no objection to a higher voltage on other
lines individual to themselves where transmission economy can be
obtained by the use of a higher voltage.
The method of suspension of the contact wires for the New
York, Westchester & Boston is quite different, however, from that now
in use upon the New Haven main line, and shows the advance in catenary
suspension design since the latter was erected several years ago. The
wires are strung in sections between "anchor" bridges, situated about
two miles apart, which take the entire strain from these wires in the
direction parallel to the track. These anchor bridges are of heavy
construction, 42 ft. in height to top of towers, and 61 ft. between
centers of side frames. Between these bridges at intervals, which are
normally 300 ft. but liable to change to meet special conditions, are
the catenary bridges which support the contact wires and hold it in
its proper position with respect to the track which it serves. They
are of lighter construction than the anchor bridges, for there is no
strain upon them, save from the weight of suspension wires, and wind
pressure. The truss is supported by latticed posts, 31 ft. in height,
and surmounted by towers with cross arms. The arms are so arranged as
to carry feeder and signal wires, two on each arm. Seventy-five feet
each side of the catenary bridge 3-in. I-beams, running across the
four tracks, are hung from the 7/8in. main steel messenger strands;
and on the beams are installed the suspension insulators. The lower
insulators hold the track messenger, 5/8-in. steel strand, to which is
pendant, by means of hangers, a copper trolley and a steel contact
wire below. There is practically no corrosion of the steel wire, for
it is constantly covered by a film of grease due to a generous amount
of this material being placed upon the pantograph shoe of the cars.
The steel wire is suspended from the conducting copper wire by means
of metallic clips which fit very tightly into V-shaped grooves in the
two wires, and afford a perfect connection between them.
 | | Raising Light Girder to Temporary
Position In Span Over New Haven Tracks |
In all cases, the masonry work has been completed first,
and often before any earth work was done. Concrete was used
throughout, not only in retaining walls, abutments, etc., but also in
highway crossings, viaducts and stations. All exposed surfaces have
been finished very carefully, and the general design has been so well
planned that the masonry work is one of the most effective features of
the road.
For embankments, temporary wooden trestling was usually
employed on work of any considerable size. The great majority of
fills are of rock; the only large earth fill being on the White Plains
branch just north of the junction point.
The work has been carried out under the direction of
J. L. Crider, chief engineer, and E. J. Langford, principal assistant
engineer. The Columbus Avenue and Hutchinson River viaducts were
erected by the American Bridge Company, under the direction of
A. H. Rhett, structural engineer of the railway company. The general
contracting work from White Plains to the junction with the New
Rochelle branch was done by the Henry Steers Company, and by Murray &
Gilbert; from this point through Mount Vernon by Lathrop & Shea; from
this point to New York by the O'Brien Construction Company.
 | | Hutchinson River
Viaduct |
|